24 men can do a piece of work in 16 days.
Thus, one man can do 1/(24x16) of the work in one day.
Similarly, a woman can do 1/(32x24) of the work in one day.
Therefore,
16 men & 16 women can do 16/(24x16) + 16/(32x24) of the work in one day.
Working for 12 days, they can do
12[16/(24x16) + 16/(32x24)] = 3/4 of the work.
Work still to be done=1/4 of the original work.
Let the no. of additional men required be x.
Then,
work done by the people in 2 days=2(x+16)/(24x16) + (16x2)/(32x24)=1/4.
x=24.
Thus, required no. of additional men=24.